 For all other information regarding this project, please see https://wiki.cac.washington.edu/display/vidconf/2008+APEC-EINET+Virtual+Symposium+Home+Page
  
 *Status Report*
 Report Update: 6.6.2008 (Post event)
 Project Health: Closing
 Recent Accomplishments: The Video Conference was a success
 Priority: Event Report / UWTV Logisitcs / Establishing Global VidConf Network
  
 || Event || Completion Date || Comments ||
 | Phases 5 has started | 6.6.2008|*[*Phase 5: Post Event*|Project Plan Phase 5 Post Event]* |
   
  